Permit Board - Panasonic Project Kansas - Tooling

Last Updated 12/3/2024 11:46:58 AM

Type
Employer
Location
Start
End
Status
PER-19799
Hot Work Permit
Alo-Cinema Installers
No Nominated Rep
D200 / Cell Warehouse
E200 / Cell Warehouse
6:30 AM
5:30 PM
12/7/2024
Pending Approval
PER-20162
Hot Work Permit
Beck & Pollitzer
Joseph Shivram
+ 4 other supervisors
B100 / Anode coating
5:01 AM
12/2/2024
5:00 PM
12/8/2024
Scheduled 1 day ago
PER-20166
Hot Work Permit
Beck & Pollitzer
Joseph Shivram
+ 4 other supervisors
A300 / Cathode Coating
5:01 AM
12/2/2024
5:01 PM
12/8/2024
Scheduled 1 day ago
PER-20195
Hot Work Permit
Beck & Pollitzer
Joseph Shivram
+ 4 other supervisors
A100 / anode mixing
5:07 AM
12/2/2024
5:07 PM
12/8/2024
Scheduled 1 day ago
PER-20196
Hot Work Permit
Beck & Pollitzer
Joseph Shivram
+ 4 other supervisors
C100 / Anode Slitting
5:16 AM
12/2/2024
5:16 PM
12/8/2024
Scheduled 1 day ago
PER-20163
Hot Work Permit
Beck & Pollitzer
Joseph Shivram
+ 4 other supervisors
A300 / Cathode Mixing 1st floor
B300 / Cathode Mixing 1st floor
5:00 PM
12/2/2024
5:49 PM
12/8/2024
Scheduled 18 hours ago